top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Buck Engineering

Primary Contractor: Byers Construction

BELL

(March - April 2002)

 

 

Additional Pictures 

Project Background

 

The site is along 3,900 feet of Brasstown Creek and includes the lower portions of Gumlog and Winchester creeks on the Opal Henson and the late Allen Bell farms.  Gumlog Creek, in particular is a major tributary of Brasstown Creek; most of its drainage area lies in Georgia and is unrestored.

 

Because of channel incision in Brasstown Creek along the Bell reach, the floodplain was only accessible during extreme flood events.  Due to agricultural practices, little to no established riparian buffer existed in some areas along this reach of the creek.  This resulted in stream bank erosion, which in turn led to increased sedimentation within the channel, and in some areas, to the channel becoming overly wide.  The increase in bankfull width had reduced sediment transport capacity, resulting in bar formations in mid-channel.  The mid-channel bars further accelerated bank erosion, altered riffle-pool sequences, and decreased the quality of aquatic habitat.  Total estimated soil loss from this reach of Brasstown Creek was 1,300 tons per year.    

 

Previously, the lower reach of Gumlog Creek was altered by beaver activity.  Water flowing along the sides of the dams had caused bank erosion and the right bank was severely eroded for about 75 feet along the outside of a bend.  The lower section of Winchester Creek exhibited a belt width that was too tight and the stream was about to cut through. 

   

Before

 Vertical bank in outside bend.

 

After

 J-Hook installed to divert erosive energies away from bank.  Bankfull bench installed to allow proper rooting depth.

 

The Bell project was completed in spring 2002.  The goals were to improve water quality and aquatic habitat by reducing sedimentation, to improve stream stability, riparian and floodplain functionality, and the natural aesthetics of the stream corridor.  The design for the Bell site called for the installation of rock vanes and deflectors to move the thalweg away from the banks, reduce near-bank stress and bank erosion, and prevent bar formation in the channel.  Bankfull benches were excavated in areas with excessively high banks on which no established buffer existed.  In these areas mature trees were not disturbed.  Root wads were installed throughout the reach.  Bank erosion in the lower reaches of the two tributary streams was mitigated by sloping and matting the banks and by installing root wads and rock vanes.  A riparian buffer was reestablished throughout the reach of the project with plantings of native trees and shrubs.

 

During HRWC’s 2005 annual project inventory, a 200-foot section of bank was found to be eroding as a result of return flow following three large storm events (flood events) in fall of 2004.  HRWC organized a volunteer workday to reshape the bank, apply erosion control matting, and install live stakes.  Students from Young Harris College provided most of the labor for the repair.

 

2008 Status

 

A 2,180-foot reach of the Bell project was monitored in 2005, 2006 and 2007, and this portion of the stream remains very stable.  In a very tight meander bend, approximately 300 feet of the restored channel has historically been subject to severe bank erosion, but this area did not see increased erosion between 2005 and 2007.  Thirteen structures provide bank protection and grade control within the monitored reach. All structures associated with the 6-year old project appear to have very good to excellent function, except for one j-hook vane in the aforementioned meander bend, which may require minor repair.  The restored stream reach is currently classified as a C4 channel.  The streambed slope is 0.003 feet/foot, with a sinuosity of 1.44.  Between 2005 and 2007, the streambed material became slightly coarser.   

 

The restored reach contains several riffles and pools.  Riffles are typically associated with the structures, while pools are present in the expected locations at meander bends.  Since 2005, riffles have generally had aggradation in the bed, while pools have generally become deeper.  Significant stream bank erosion is not observed within the channel.

 

Vegetation in the buffer is generally dense and reproductive trees line both banks.  However, much of the understory vegetation is invasive, dominated by exotic Chinese privet (Ligustrum sinense), a mixture of exotic and native dewberry and blackberry (Rubus spp.), and native river cane (Arundinaria gigantea).

 

An increase in the Total Suspended Solids concentration between upstream and downstream monitoring stations was reported at the Bell project reach.  Five of the seven samples had higher TSS downstream with an average of 241% increase.  These observed increases underscore the importance of continuing to pursue restoration work in the Georgia portion of the watershed.

 

In 2007, the benthic macroinvertebrate assessment at Bell yielded a bioclassification of Good/Fair, the same as in 2005.  Between 2005 and 2007, EPT taxa richness increased slightly, while EPT abundance decreased slightly.

 

3-Year Study Recommendations

 

In addition to continuing to monitor this reach in subsequent years, recommended actions include:

  • Remove dense privet and replace with native shrubs, trees, and river cane

  • Evaluate options for stabilizing both sides of the stream bank at the meander bend near station 11+00

  • Closely monitor the currently stable areas with high shear stress; specifically in three locations between stations 16+85 and 18+59, 15+22 and 16+09, and 9+50 and 14+30

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC