top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Buck Engineering

Primary Contractor: Roger Swanson Construction Company

CAMPBELL

(February - April 2001)

 

Additional Pictures

Project Background

 

This site is along a 3,900-foot reach of Little Brasstown Creek immediately upstream of its confluence with Brasstown Creek.  The primary property owner is the John C. Campbell Folk School in Brasstown, NC. 

 

Little Brasstown Creek flows through a wide alluvial valley as it nears its confluence with Brasstown Creek.  The lower reach of Little Brasstown Creek lacked an adequate riparian buffer.  Severely eroding stream banks and channel instability indicated substantial stream degradation.  Past channel modifications (channelization) of the lower reaches of the creek were instrumental in the degradation.

 

Restoration goals for this project were to improve water quality and aquatic habitat in Little Brasstown Creek by reducing bank erosion and sedimentation, improve stream stability and  riparian and floodplain functionality. 

 

The Campbell project is one of the oldest HRWC stream restoration sites (constructed in winter 2001) and was the first location where both HRWC and the consultant, Buck Engineering, attempted a complete “Priority 1” pattern change.  The stream bed consisted almost entirely of sand and construction contractors were unable to find bedrock on which to seat the majority of the structures.  Because of the much slower, glide/pool nature of the reach, and the lack of a solid foundation, log structures were installed, rather than rock structures.    

 

(Picture by Buck Engineering)

Before

(Picture by Buck Engineering)

During

After

 

At various points throughout the 7-year period since construction was completed, mowing of the walking path and viewing areas (that was allowed in the original agreement) has been excessive and has encroached on the riparian buffer.  HRWC and the Folk School have replanted buffer vegetation in these areas and, each time a new maintenance person gets overly eager, HRWC continue to work with the Folk School to correct the error.

 

Following storm events in fall of 2004, HRWC attempted to repair the lowest, most intact log cross vane structure to no avail and personnel have been routinely checking on the site ever since.  Numerous visits from engineers with Buck Engineering and others familiar with stream restoration techniques have failed to result in a solid recommendation for further action.  

 

2008 Status

 

Approximately 2,200 feet of the Campbell project were monitored in 2005, 2006 and 2007.  The monitored portion of the Campbell stream restoration project is largely unstable, with several areas of concern.  A need for immediate repair exists, as well as a long-term repair and maintenance strategy to ensure the success of the project.  All 17 structures that were monitored have experienced some degree of failure, with most currently not providing any positive functions.  The structure failures appear to have exacerbated localized stream bank erosion, as well as having allowed downcutting of the channel bed.  Between 2005 and 2007, most structures show little or no change. The restored stream is currently classified as an E5/C5.  The streambed slope is 0.002 feet/foot, with a sinuosity of 1.18.  The streambed is characterized by very fine sand.

 

The restored reach lacks a well-defined riffle and pool sequence, though longer riffles and pools developed between 2005 and 2007.  The riffles and runs are composed of a very fine substrate, which does not provide ideal macroinvertebrate habitat.  Stream bank erosion is occurring sporadically throughout the channel, though increased vegetative growth is likely limiting erosion.

 

Despite the failure of most of the structures, this reach of Little Brasstown Creek is in much better shape today than prior to restoration.  Planted woody vegetation, natural woody regeneration, and herbaceous growth are generally successful and lush on the buffer and banks at the Folk School.  The heavy shade helps to mitigate water temperatures within the restored reach. 

 

The 2007 macroinvertebrate assessment yielded a bioclassification of Poor, compared to Fair in 2006 and Good/Fair in 2005.  The number of EPT taxa and EPT taxa abundance dramatically decreased in 2007 from already low levels in 2005 and 2006.  Although significant problems with bank erosion and high Total Suspended Solids were identified over the 3-year monitoring period, no change was reported in any other category.  The reason for the declining trend in the macroinvertebrate population at Campbell between 2005 and 2007 is unknown.

 

3-Year Study Recommendations

 

In addition to continuing to monitor this reach in subsequent years, recommended actions include:

  • Continue negotiations with the Folk School to keep mowing in check

  • Re-stake some areas of bare bank

  • Remove invasive patches of kudzu, Japanese honeysuckle, privet, Lespedeza, and multiflora rose

  • Monitor for further invasion from upstream of kudzu, privet and Lespedeza

  • Repair Structure K

  • Evaluate implications of beaverdams at STA 5+12 and 12+03

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC