top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Buck Engineering

Primary Contractor: Bell Creek Farms

CARRINGER/MITCHELL

(February - March 2004)

 

Additional Pictures 

Project Background

 

The Carringer/Mitchell project site is along Little Brasstown Creek on the properties of Jim and Janice Carringer and Dr. Brian Mitchell and Dr. Nancy Troxler.  It is situated upstream of the Campbell project and downstream of the Sheppard project in the Little Brasstown Creek watershed; however, there is nearly a mile-long reach immediately upstream for which restoration has been designed, but not constructed. 

 

The Carringer-Mitchell reach of Little Brasstown Creek has a drainage area of 8.6 square miles and drains mostly pastureland and forest; there is little impervious area. The reach was channelized historically and, prior to construction, cattle had full access from the left bank of the stream at this location.  Approximately two-thirds of the right bank had an excellent wooded riparian buffer as the stream is basically situated at the base of the ridge. The left bank had severe to moderate erosion and the riparian buffer was inadequate along approximately two-thirds of the length. Bank sloughing was undermining the existing, inadequate fence along the left bank and large pieces of land were being lost with each significant rain event.

 

HRWC was somewhat limited in what could be accomplished at the Carringer/Mitchell site for two reasons: (a) one adjacent landowner was not willing to sign an easement and (b) Mr. Carringer did not want to change the stream’s pattern because of the amount of pastureland he would effectively lose. Therefore, the project was largely a stream bank restoration project, although a few in-stream structures were installed along the Carringer farm to improve the bed profile and provide bank protection. Transplants, live stakes and brush layers were used to provide bank stability. In the lower one-third of the project reach along the Mitchell property, a combination of live stakes, fascines and brush layers were used to stabilize the existing right bank of the channel. Construction during the winter months  of 2004 was critical to the success of these bioengineering techniques.

 

Before

Notice the vertical bank and obvious erosion.

 

After

Bank was sloped and stream energy

directed to the center of the channel.

 

Native tree species were planted along the Carringer farm and a portion of the Mitchell property that did not have an adequate buffer. A new, 4-strand barbed wire fence was constructed according to NRCS standards along the Carringer property to protect the newly planted buffer; alternative watering for livestock is available on the pasture.

 

2008 Status

 

The entire 2042-foot restored reach was monitored in 2005, 2006 and 2007.  The Carringer/Mitchell project is moderately stable, with localized areas of bank erosion where repair work should be considered.  The restored reach contains eleven in-stream structures.  The majority of the structures are single arm rock vanes, which are primarily serving as boulder toe protection for the banks, rather than influencing the path of the water.  Between 2005 and 2007, some structures showed deterioration.  Structures D, H, I, and K noticeably deteriorated; structure K developed a serious piping problem. The restored stream is currently classified as an E4 channel.  The streambed slope is 0.003 feet/foot, with an extremely low sinuosity of 1.01.   The median particle size is currently coarse gravel, which represents significant coarsening since 2006.

 

The restored reach has two constructed riffles and other stable riffles.  Deep pools dominate the upper half of the restored reach, while riffles and runs are generally predominant in the lower half of the reach.  The few pools that did exist in the lower half of the reach became shallower or disappeared between 2005 and 2007.  The stream pattern was not changed as part of the restoration activities, so the stream remains extremely straight.  Localized areas of bank erosion do exist, but are generally minor and not attributable to structure failure.

 

Vegetation is well developed on the restored terrace, with some problem areas at the fenced edge of the buffer and on the banks.  The buffer is fenced on the left bank.  On the downstream right terrace, a park-like planted area is mowed by landowners and some mowing damage to planted trees has resulted.  Air and water temperatures are being moderated by the riparian buffer at Carringer/Mitchell.

 

Storm event samples collected downstream of the restored site were lower in Total Suspended Solids (TSS) than samples collected upstream by an average of 39%.  None of the eight sampling events showed an increase in TSS throughout the project reach.  Although the Carringer/Mitchell project is effectively removing sediment from the system, levels of TSS on the upper end of the project indicate a need for restoration in the W. Carringer/Tanney reach.

 

The macroinvertebrate assessment yielded a bioclassification of Good for all three years of monitoring.  Between 2005 and 2007, the number of EPT taxa and EPT abundance both decreased.

 

3-Year Study Recommendations

 

In addition to continuing to monitor this reach in subsequent years, recommended actions include:

  • Perform emergency repair to stop piping and bank erosion at left arm of Structure K

  • Remove  exotic invasives to prevent future problems

  • Install guards on trees in mowed area on Mitchell property to prevent further damage

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC