top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

CRITICAL BARE AREAS

 

Garland Hogsed     David Stiles      Herman Ford     John Wood     James Payne

 

Landowners of bare, eroding areas within 300 feet of streams in the watershed were contacted and offered financial support through the Brasstown Watershed Restoration Project to assist in stopping the erosion and improving the condition and productivity of their land. Conservation treatments commonly used include grading and filling and the preparation of seedbeds. Contour ripping and diversions were sometimes used to enhance infiltration and slow runoff. Hydroseeding was occasionally required on steep slopes.  In most cases, the landowner, the Coalition, NRCS, and Clay County Soil and Water Conservation District signed contracts. A cost-share agreement of 80/20 was used with the landowner agreeing to share 20 percent of the cost of the project with cash or in kind services, and to maintain the practices for the life of the agreement.  The NRCS, with assistance from the District, provided the Conservation Plans, layout of the projects, and technical oversight.

 

Hogsed and Stiles critical bare area project lands before treatment. 

[Note eroding hillsides in distance.]

 

GARLAND HOGSED Project

 

This site is a 40-acre steep mountain pasture drained by the headwaters of Long Branch.

 

Conditions of Site Prior to Project

This 40-acre plot had been clear cut, about five years prior to first inspection, and not replanted.  Slopes were very steep and the owner was advised that replanting with trees would be the best course of action to stabilize the land.  However, Mr. Hogsed was determined to establish pasture.   Rills and gullies had formed causing severe erosion and little topsoil was left.  Some of the gullies were 3-4 feet deep, 4-6 feet wide, and 200-500 feet long. Tracks were visible from previous attempts to apply seeding and chemicals.  These tracks ran vertical to the slopes rather than along contours or the horizontal.  Mr. Hogsed also has a borrow pit for fill material located about 50 feet from the branch.  This pit is located such that flows from storm events are concentrated into a raw gully that flows directly into the pit, which then overflows directly into Long Branch.  

 

Although the Long Branch drainage comprises only first and second order streams and the drainage area is small, this site was deemed by NRCS to be one of the worst sources of sediment in the Brasstown Creek watershed. 

Before

After

 

Conservation Treatments Installed

To meet the objectives for this project, the site was graded and a seedbed was prepared for the planting of fescue. Critical areas were stabilized, gullies filled, and the land shaped to prevent erosion.  Contour ripping was done to help infiltration and to reduce peak flows off the slopes.  Inspections by NRCS through 2002 have shown continual improvement at this site.

 

Work has started to remediate erosion and soil loss through the borrow pit.  This project will entail the construction of a sediment pond or diversion above the borrow pit with outlet piping around the pit to a rip rapped gravel pad which will serve to filter runoff water prior to its flow into Long Branch. This work is covered under another contract and was completed in 2003. This project restored 40.0 acres.

 

Top of the Page

 

DAVID STILES Project

 

This site is a 77.7-acre steep mountain pasture drained by the headwaters of Long Branch and adjacent to the Garland Hogsed Project.

 

Conditions of Site Prior to Project

Most of the trees had been cleared off this 77.7-acre plot to convert the landscape to pasture.  Slopes were very steep and rills and gullies had formed causing severe erosion. Erosion was also occurring from recent road construction into the property.

 

Although the Long Branch drainage comprises only first and second order streams and the drainage area is small, this site was deemed by NRCS to be one of the worst sources of sediment in the Brasstown Creek watershed. 

 

Conservation Treatments Installed

To meet the objectives for this project, the site was graded and a seedbed was prepared for the planting of fescue. Critical areas were stabilized, gullies filled, and the land shaped to prevent erosion.  A diversion was installed to help reduce peak flows off the slopes. 

 

 

Work is continuing on this site under another contract.  This project will include the installation of two sediment ponds with livestock exclusion fencing.  Also, hydroseeding of about two acres of severely eroding slopes will be done followed by the replanting of trees. 

 

Mr. Stiles plans to put horses on this property.  When this occurs, he will be eligible for additional monies, through NC Ag Cost Share and EQUIP programs, to install more conservation practices to improve this site.

Top of the Page

 

herman ford project

 

This site is a pasture on the farm of Herman Ford in the headwaters of the Beach Creek watershed.

 

Conditions of Site Prior to Project

Three road culverts that drained onto Mr. Ford’s pasture were causing significant erosion problems.  Gullies and rills had formed in the pasture and head cutting below the culverts was occurring.  Two ditches were eroded and needed stabilizing.  The pasture is about 40 acres with about half in fair to poor condition.  There were four acres of bare area ranging from 15-30 percent slopes within 300 feet of Beach Creek.  Cattle had been previously fenced out of he creek, but vegetation was not well established on the streambanks.

 

Conservation Treatments Installed

To meet the objectives for this project, the installation of a lined waterway, a grassed waterway, a stream crossing and a diversion was necessary, followed by critical area stabilization and planting.  This project restored 13.3 acres.

 

Top of the Page

 

JOHN WOOD Project

 

This site is an eight-acre plot that borders a tributary to Beach Creek on the farm of John Wood.

 

Conditions of Site Prior to Project

The site borders Beach Creek and has slopes that range from 8-20 percent.  Mr. Wood was attempting to increase pasture acreage (approximately eight acres) by clearing off early succession tree species from a slope within 300 feet of the creek.  Previous logging practices had caused severe ruts going into the site and clearing this area had increased erosion and sediment going into Beach Creek.

 

Conservation Treatments Installed

To meet the objectives for this project, the site was graded and a seedbed was prepared for the planting of red clover and orchard grass. Critical areas were stabilized, gullies filled, and the land shaped to prevent erosion. This project restored 8.0 acres.

 

Top of the Page

 

JAMES PAYNE Project

 

This site is a 23-acre plot drained by the headwaters of Payne Branch.

 

Conditions of Site Prior to Project

This 23-acre plot had been clear cut and not replanted.  Rills and gullies had formed causing severe erosion.  Road ditches were also eroding.

 

Conservation Treatments Installed

To meet the objectives for this project, the site was graded and a seedbed was prepared for the planting of fescue. Critical areas were stabilized, gullies filled, and the land shaped to prevent erosion.  A road ditch was also reshaped and armored with riprap. This project restored 23.0 acres.

Brasstown Project Summary

Top of the Page

 

Copyright © 2004-2007 HRWC