top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Buck Engineering

Primary Contractor: Byers Construction

HYATT

(March 2002)

 

 

Additional Pictures 

Project Background

 

This site is along 2,700 feet of Brasstown Creek on the Bass Hyatt farm approximately 3.5 miles west of the community of Warne, NC.  Like Bell, this project was completed in spring 2002.

 

Prior to restoration, there was active bank erosion along most of this reach, and pasture grazing had resulted in little or no riparian buffer along the upper portion of the reach.  The downstream section of the project had more established buffer than the upstream section and there was also less bank erosion.  Some areas of the stream had become overly wide because of the excessive bank erosion and this resulted in the formation of several mid-channel bars.  The total estimated soil loss from this reach of Brasstown Creek was 830 tons per year with an average rate of erosion of 876 lb/ft/yr.

 

Before

After

 

 The goals of this project were to improve water quality and aquatic habitat by reducing sedimentation, to improve stream stability, riparian and floodplain functionality, and the natural aesthetics of the stream corridor.  Meeting these objectives along the 2,700 feet of stream involved removing mid-channel bars and a log debris jam, narrowing the channel, stabilizing eroding stream banks, and reestablishing an adequate riparian buffer.

 

The design included installing cross vanes to stabilize eroding banks and to center the thalweg in the channel.  A double wing deflector was also used in one section to center the thalweg and narrow the channel.  J-hook vanes and root wads were installed throughout the reach to stabilize eroding stream banks.  Area disturbed by the removal of the debris was properly stabilized.  A riparian buffer zone was reestablished along both banks.  Fencing and alternative watering for livestock was also provided.

 

 

2008 Status

 

A 1,717-foot reach of the Hyatt project was monitored in 2005, 2006 and 2007.  It is very stable.  Nine structures provide bank protection and grade control within the monitored reach.  With the exception of the uppermost j-hook vane, which appears to be undersized, all structures associated with this 6-year old project have very good to excellent function.  Generally, structures did not change between 2005 and 2007.  The restored stream reach is currently classified as a C4 channel.  The streambed slope is 0.002 feet/foot, with a sinuosity of 1.26.  Between 2005 and 2007, the median streambed material remained the same, at very coarse gravel.

 

The restored reach contains several riffles and pools, though riffles and runs compose the majority of the project length.  Riffles are typically associated with the j-hook vanes, while pools are present downstream of the two cross vanes and in the one meander bend.  The 2007 channel pattern is very similar to that of previous years.  Stream bank erosion is not occurring on a significant scale within the channel.

 

Vegetation in the buffer is well developed, and there are many remnant trees.  Because restoration disturbance was limited in scope, planted vegetation is absent from the unrestored side and localized on the restored side of the stream.  Survival of planted vegetation is good, and there is moderate natural regeneration in the sampling plots.  Herbaceous growth in 2007 was less dense than in previous years due to drought, but the buffer was still well vegetated.

 

Maximum air temperatures were significantly lower in the buffer zone at Hyatt than in the adjacent field.  This project had the highest measured shade cover (85%) of all the monitored sites.  Peak water temperatures were also consistently lower downstream of the restored reach on the Hyatt project.

 

In 2007, the macroinvertebrate assessment downstream of the Hyatt project yielded a bioclassification of Good, compared to Good in 2006 and Excellent in 2005.  As was observed upstream at Bell, EPT taxa richness and abundance decreased between 2005 and 2007.

 

3-Year Study Recommendations

 

In addition to continuing to monitor this reach in subsequent years, recommended actions include:

  • Remove fescue and stiltgrass and re-seed with temporary seed and a native perennial seed mix, or plant river cane (Arundinaria gigantea), to increase diversity at the site

  • Routinely monitor the currently stable areas with high shear stress; specifically at two locations between stations 8+76 and 9+45, and between stations 13+33 and 14+60

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC