top

Search the HRWC web site 

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

LONG BRANCH

 

Long Branch is a second order tributary of Crawford Creek which flows into Brasstown Creek in the Warne community.  Long Branch is a relatively steep mountain stream that drains the east side of Beach Mountain.  The drainage area is less than one square mile.  Before restoring the lower end of Long Branch along Don & Linda Anderson's pasture (Long Branch 2 project), the Coalition recognized the need to fix a severe problem upstream on Steve and Joyce Mulkey's property (Long Branch 1 project).

 

 

 


 

Project Design: EcoLogic Associates, P.C.

Primary Contractor: Byers Construction

LONG BRANCH 2

(2002)

 

Project Background

 

Before restoration, the stream was severely incised and unstable, stream banks were actively eroding and there was an inadequate riparian buffer on the right bank.  A road borders the stream on the left bank, but as much riparian vegetation as could be expected was present along most of this side between the stream and the road.  More than 100 acres of forest had recently been cleared in the headwaters of Long Branch; and, HRWC and its partners worked with the landowners to stabilize the areas and establish pasture through critical bare area projects. In addition, a failed culvert upstream was replaced prior to restoration. These events in the upstream watershed were likely the primary causes of instability at this site; however, the pasture use and inadequate buffer within the project reach also contributed.

 

Banks were sloped, cross vanes installed and bankfull (floodplain) benches established to restore a more stable cross-sectional geometry and to help establish a good riparian buffer.  Native trees and shrubs were planted in the riparian buffer; however, the newly sloped banks were rocky and soil conditions were poor.  A total of 475 linear feet of Long Branch was restored. 

 

 

2008 Status

 

The entire restored reach at Long Branch was monitored in 2005, 2006 and 2007.  The reach is moderately stable, with eight cross vanes successfully holding grade. The stream continues to undergo aggradation, as the channel evolves toward a stable dimension.  Since 2005, most structures show little or no change.  Structures C and G noticeably deteriorated between 2005 and 2007, but these changes have not directly led to bank erosion or structure failure.  The restored stream reach is currently classified as a C4b channel.  The streambed slope is 0.028 feet/foot, with a sinuosity of 1.03.  Between 2005 and 2007, the streambed material became significantly coarser, changing from a sand to gravel bed stream.  The median particle size in 2007 represents very coarse gravel.

 

The restored reach is dominated by riffles and runs and contains a few shallow pools.  Many of the cross vanes do not have associated scour pools.  This straight reach contains one significant (existing) meander bend, which does have a pool.  As a result of this tight meander bend and other very slight bends, there are instances of high shear stress within the reach.  Due to well-vegetated banks and a low, wide floodplain, however, bank erosion is largely non-existent.

 

Vegetation in the buffer at Long Branch is patchy and some planted woody material is unhealthy.  While tree and shrub plantings do not appear successful, the banks are well covered and natural regeneration creates an exceptionally high stem count.   Overall, the site appears much better than could be predicted from its 2005 appearance, but is now threatened by exotic invasives.  A new fence was built in 2007, slightly inside the planted buffer. 

 

All three storm event samples obtained at Long Branch indicated that the Total Suspended Solids concentrations were higher downstream of the restored reach, with an average of 164%.  This is attributed primarily to runoff from the adjacent road.

 

Between 2005 and 2007, EPT taxa richness and the EPT abundance both increased.

 

3-Year Study Recommendations

 

Recommended actions at Long Branch include:

  • Removal of the native but invasive hog peanut, to improve tree health

  • Early removal of kudzu and honeysuckle

  • Consider removal of some unhealthy trees and replace with better stock

  • Continue to monitor in subsequent years, with particular attention given to Structures C, G and H and high shear stress areas

  • Evaluate road runoff situation to determine if BMPs could be installed to reduce TSS concentrations instream


Project Design: EcoLogic Associates, P.C.

Primary Contractor: Byers Construction

LONG BRANCH 1

(October 2001)

 

 

Conditions of Site Prior to Project

During a high intensity rainfall event (3.5 inches in 45 minutes) in August of 2001, a four-foot diameter, corrugated, metal culvert, clogged with woody debris, failed from overtopping.  As a result, a section of gravel driveway approximately 8-10 feet wide, upstream of the culvert, washed out, leaving an exposed and badly eroding section of streambank.  Long Branch is a tributary to Crawford creek, which flows into Brasstown Creek in the lower reaches of another Trust Fund Grant project (Warne Project).  Additional Trust Fund monies were being spent restoring two badly eroding plots of land (Stiles and Hogsed projects) in the headwaters of the Long Branch watershed.  Work in this watershed was of high priority to the Coalition because of the heavy contribution of sediment coming from the critical areas in the headwaters and its location in the Brasstown Creek watershed (immediately upstream of a completed project).  Also, another project, contiguous with the failed culvert site, was being planned on the stream (Long Branch # 2, in planning phase at this writing).   Considering all these factors the Coalition decided to spend grant monies to aide in the replacement of this culvert and restoration of the eroding banks.

 

Before

Inadequate culvert size and improper maintenance caused this driveway to blow out leaving an eroding and unstable bank.

After

 Arched culvert installed to accommodate a 10-year short duration rainfall event.

 

 

Instream Technologies Applied

A corrugated metal pipe (aluminized steel), with an 86-inch by 63-inch pipe arch, was installed at the site.  The structure satisfied NC DOT hydraulic criteria for private drives and passed the criteria for the 10-year, short duration storm, which was the type of high intensity storm that caused the culvert failure.  Banks adjacent to the pipe were properly sloped and stabilized with filter fabric and Class B riprap.  ABC stone was spread and compacted on the driveway atop the culvert.

 

Linear Feet of Stream Restoration

Approximately 75 feet

 

Linear Feet of Riparian Buffer Restored and/or Protected

Approximately 150 feet

 

Buffer Vegetation

Due to the linear limits and nature of this project, little riparian restoration was called for.

Brasstown Project Summary

Top of the Page

 

Need HRWC Web Site Assistance? Email the Web Site Administrator.

Copyright © 2004-2010 HRWC