top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Natural Resources Conservation Service (NRCS)

Primary Contractor: West Contracting

MATHOT

(August - September 2000)

 

 

The Mathot project was the Coalition's first stream restoration project and is situated along Brasstown Creek about 0.4 miles upstream of where Little Brasstown Creek flows in.  The 5-acre tract is owned by Mitchell Mathot.

 

Conditions of Site Prior to Project

Because of land use activities along the stream, including removal of trees on the streambank and maintenance of a yard up to the edge of the stream, approximately 820-feet of eroding bank was present along Brasstown Creek on the Mathot property.

 

Before 

Lack of riparian buffer has caused

significant erosion to property.

 

After 

Cross vane installed to protect both banks. Pool and point bar were shaped to improve stream features.  Bankfull bench was installed to allow vegetated growth.

 

Instream Technologies Applied

Streambank and channel restoration methods were determined following natural channel design methodologies as proposed by Rogsen.  Procedures included installation of a cross vane, a wing deflector, and root wads. The bank was pulled back at a 3 to 1 slope from bankfull to top of bank.  See “As-Built” schematic for details.

 

Linear Feet of Stream Restoration

820 feet

 

Linear Feet of Riparian Buffer Restored and/or Protected

1,640 feet

 

Buffer Vegetation

A 50-foot riparian buffer was established on this site.  A landscape architect was hired to create the landscaping plan and plant list.  During construction, sod mats, shrubs, and trees less than 3” in diameter were saved for transplanting, where practicable. Potted shrubs and wetland species were planted along the streambank above bankfull elevation.  Bare root vegetation was planted along the streambank below bankfull elevation.

Brasstown Project Summary

Top of the Page

 

Copyright © 2004-2007 HRWC