MURPHY HIGH SCHOOL
TRACK
PROJECT TIMELINE
September 2008 - August
2010
|
February 2009
-
Contract with environmental consultants for bank
stabilization and stormwater BMP design
-
Surveyors on site at various times
-
Put together a detailed timeline of activities and
brief project partners
March
2009
-
Identify teachers/students at Murphy
HS that will be involved in
various phases of the project
(Meeting held March 18th
at 9:00am.)
-
Complete
the engineering design for bank stabilization and
riparian buffer restoration at Murphy HS track
-
Complete
the preliminary plans for stormwater drainage/BMPs
April
2009
-
Hold volunteer workday
#1
(Wednesday, April 22nd
at 8:00-3:00)
-
Remove
trash & debris, including dead trees
-
Remove
large specimens of invasive plants such as privet,
kudzu, Japanese honeysuckle and multiflora rose.
[Cut stem herbicide treatments applied at this time
for partial control of larger specimens.]
-
Meet
with school administrators to discuss engineered
plans
-
Apply
for permits related to bank stabilization work
May
2009
-
Hold
volunteer workday #2
(Coordinate with
school-wide workday?)
-
Continue
removal of invasive plants
-
Install
live stakes in the banks not affected by
stabilization activities
-
Restoration
coordinator to apply foliar herbicide treatments for
control of smaller invasives and spot check of
previously treated plants to check for re-sprouting
June
2009
-
Begin
implementation of the stormwater drainage/BMPs at
the site
-
Avoid
activities around graduation on June 13, 2009
July
2009
-
Continue installation
of stormwater drainage system and BMPs, including
the new parking lot
-
Begin
bank stabilization work
August
2009
September - November
2009
-
Restoration
coordinator to apply second round of foliar
treatments specifically for control of smaller
Chinese privet and Japanese honeysuckle and check
for re-sprouting of previously treated areas
-
Design
and install signage
-
Determine
if a second application to Section 319 Program is
needed for additional site work
December - February
2010
-
Hold
volunteer workday #3
-
Plant
30-foot riparian buffer along approximately 1,500
linear feet of the Valley River at the Murphy HS
track
March - May
2010
June - August
2010
-
Monitor
success of native vegetation in the riparian buffer,
supplementing plantings when necessary
-
Hold
on-site educational/informational event
|
|