top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Jason Wheatley, Natural Resources Conservation Service (NRCS)

Primary Contractor: Stanley Construction

OLAND

 (January - February 2001)

 

 

Additional Pictures 

Project Background

 

The Oland site is on a 37-acre parcel of land off of Old Highway 64 West near the community of Brasstown, NC.  The project is located on the east and west banks of Brasstown Creek, about one mile upstream from the Brasstown community and the confluence of Brasstown Creek and the Hiwassee River.  The Oland project was constructed in winter 2001 and is unique in that it is the only monitored project not designed by a private consulting firm.  Natural Resources Conservation Service personnel designed the structures and provided primary construction oversight for the project.

 

The site is directly downstream from a very old privately maintained bridge across Brasstown Creek.  The constriction of the creek at the stone bridge piers was the primary cause of bank erosion and channel widening problems downstream.  During a bankfull event, the channel width was reduced from 72 feet to 36 feet at this bridge.  The natural channel downstream could not support the increased velocity and force of the flow resulting from this constriction.  The left bank had been severely eroded for a distance of about 300 feet below the bridge. At that point, the channel width at bankfull was over 100 feet.  The creek had lost its sediment carrying capacity and had begun to aggrade dramatically.  A shallow transverse bar crossed the entire channel at a point where a pool should naturally occur.  As the banks eroded, several large trees fell into the creek, adding to the instability of this section of stream.  Bankfull elevation was very near low bank elevation.  Flows from storm events in excess of the 1.5 year storm (typical return interval for bankfull event) would spill over the low bank onto the adjacent flood plain. 

 

Before

Bankfull width is 104 feet across.

Large mid-bar is sending velocities into both banks.

After

Crossvane installed to protect both banks.

Deposition of sand and wood in less than one year.

Goal is to eventually have a bankfull width of 77 feet.

Since the historic bridge was a fixture not likely to be removed at any time in the foreseeable future, it was necessary to restore dimension and profile of the stream downstream of the bridge.  The goal was to dissipate the energy downstream of the bridge constriction in a way that would not continue the cycle of bank erosion and channel widening that had occurred in the past. 

 

A rock cross vane was installed at a location downstream of the bridge and upstream of the eroded bank area.  This structure would effectively turn flows away from the banks and dissipate energy in a mid-channel, plunge pool during bankfull events.  The top of this structure tied into the banks at bankfull elevation and at the appropriate bankfull width (75 feet) for the drainage area.  Tree revetments were secured along the eroded bank section in sufficient quantity to reduce flow velocities, to restore optimal bankfull channel width, and to trap sediment so that a stable soil medium could be established to support permanent vegetation.  Root wads installed into the eroded bank for stabilization helped anchor the revetment.  A 50-foot riparian buffer was established as part of the restoration.

 

 

2008 Status

 

The entire 600 feet of restored stream at Oland was monitored in 2006 and 2007, and it is very stable.  The cross vane that was constructed successfully provides grade control, maintains velocity, and protects stream banks.  The restored stream reach is currently classified as an E4 channel.  The streambed slope is 0.004 feet/foot, with a sinuosity of 1.34.  The median particle size is currently very coarse gravel. 

 

The restored reach contains three riffles, one deep scour pool, and a few shallower pools.  Riffles are associated with the straight portions of the channel, while the pools are present downstream of the cross vane and in the meander bend.  The 2007 channel pattern and profile is very similar to that observed following construction in 2001.  Stream bank erosion was not observed within the channel.

 

In 2007, the macroinvertebrate assessment downstream of the Oland project yielded a bioclassification of Good, compared to Good in 2006 and Excellent in 2005.  Between 2005 and 2007, EPT taxa richness and abundance decreased as with other Brasstown Creek sites.

 

Disturbance of existing vegetation during Oland construction was minimal, and the vegetation has recovered well, stabilizing the banks and providing structure on the terrace.  Oland is distinctive among Hiwassee projects for its diversity and concentration of exotic invasives.  Beaver activity continues to remove planted trees.

 

3-Year Study Recommendations

 

In addition to continuing to monitor this reach in subsequent years, recommended actions include:

  • Remove invasives; Oriental bittersweet (Celastrus orbiculatus) in particular

  • Place beaver fence around young planted trees

  • If the property is sold, conduct an early walkthrough with the new owner to identify and preserve planted vegetation

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC