top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: ARCADIS G&M

Primary Contractor: Ownbey Bulldozing

WARNE

(February - April 2001)

 

 

Additional Pictures 

Project Background

 

The site is located along a 4,500-foot reach of Brasstown Creek and flows through eight properties in the community of Warne, NC.  The project is the most upstream of all projects along Brasstown Creek and is only about one mile from the NC-GA state line.  It is also one of the oldest projects, having been constructed early in 2001. 

 

Due to past farming practices in the community, including livestock access to the creek and inadequate riparian vegetation along its banks, this section of Brasstown Creek exhibited severely eroding stream banks prior to restoration.  Soil loss through erosion for this reach of the creek was estimated to be at least 1,300 tons per year.  The goals for restoration work were to improve water quality and aquatic habitat by reducing bank erosion and sedimentation, improve stream stability and riparian and floodplain functionality. 

 

Before

After

 

This project resulted in a partnership with eight landowners along the creek.  Restoration consisted of installing root wads and constructing rock vanes, j-hook vanes, and cross vanes.   Livestock exclusion fencing was installed and a 50-foot riparian buffer was reestablished using native trees and shrubs.

 

2008 Status

 

Approximately 2,200-linear foot reach of this project was monitored in 2005, 2006 and 2007.  This portion of the Warne stream restoration project is stable, with a few areas of concern.  Thirteen structures provide bank protection and grade control within the monitored reach.  Several single arm rock vanes have experienced some deterioration, typified by boulder movement and localized bank erosion; however, the three cross vanes continue to successfully hold grade after nearly seven years.  The restored stream reach is currently classified as a C4 channel.  The streambed slope is 0.003 feet/foot, with a sinuosity of 1.30.  Between 2005 and 2007, the streambed material became slightly finer.

 

The restored reach contains several riffles and pools.  Riffles are typically associated with the cross vanes and j-hook vanes, while pools are present in the expected locations at meander bends.  Between 2005 and 2007, the pools generally became deeper and moved toward the outside of the meander bends.  Riffles remained in the same planform locations while generally showing slight aggradation.  Some stream bank erosion is occurring sporadically throughout the channel, typically in areas with structural failures and poor vegetative growth.

 

Few areas were disturbed by construction, so remnant trees are common and planted vegetation is localized.  Vegetation is generally thick and the banks are stable.  Understory vegetation is dominated by blackberry and dewberry (Rubus spp.), privet (Ligustrum sinense), river cane (Arundinaria gigantea) and early successional species.  Based on water temperature data collected during the monitoring period, the riparian buffer appears to be moderating peak temperatures.

 

Even with a large sediment load coming into the reach from unrestored portions of the watershed in Georgia, at Warne, four out of six sampling events resulted in decreases in Total Suspended Solids between the upstream and downstream ends of the project.  An average decrease in TSS of 16% was recorded over the monitoring period.

 

In 2007, the macroinvertebrate assessment yielded a bioclassification of Good, the same as in 2006.  Between 2005 and 2007, EPT taxa richness and abundance both saw a net increase.  Macroinvertebrate bioclassifications are comparable at Brasstown Creek sites further downstream of the Warne project

 

3-Year Study Recommendations

 

In addition to continuing to monitor this reach in subsequent years, recommended actions include:

  • Remove privet and replace with native plantings to increase habitat quality and prevent spread of exotics to nearby landowners

  • Encourage vegetation growth on bare banks and at the areas of localized stream bank erosion, typically near the rock structures

  • Closely monitor those areas with high near-bank shear stress; specifically at three locations between stations 13+50 and 14+40, 17+49 and 18+15, and 1+24 and 6+20

  • Evaluate the potential implications of a beaver dam at Structure G

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC