top

1853 NC Hwy 141, Murphy, NC 28906  •  Phone/Fax: (828) 837-5414

 

BRASSTOWN CREEK WATERSHED RESTORATION PROJECTS:

 

BellGreasy CreekHyattLong BranchLower BrasstownMathotOlandTrout CoveWarneWoodCritical Bare Areas

PROJECTS ON LITTLE BRASSTOWN CREEK:

 

CampbellCarringer/MitchellMason/StalcupSheppard

Project Design: Buck Engineering

Primary Contractor: Byers Construction

WOOD

(March 2002)

 

Additional Pictures 

 

The Wood project is situated along Brasstown Creek immediately downstream of the Warne project site on land owned by John Wood.

 

Conditions of Site Prior to Project

The Wood reach of Brasstown Creek, which is 400 feet in length, lacked an established riparian buffer and had become overly wide.  Stream bank erosion was highest along the right bank.  The average rate of erosion along the site was estimated at 386lb/ft/yr (130 tons per year).

 

Before

Before restoration work began, the stream’s energy and a lack of streamside vegetation resulted in significant streambank erosion and loss of land.

 

 

After

A rock structure called a cross-vein was installed in Brasstown Creek to direct the stream’s energy back into the center of the channel and trees were planted on the streambanks.  You can see the bank being re-built by the stream behind the “arm” of this structure.

 

Instream Technologies Applied

Streambank and channel restoration techniques were determined following natural channel design methodologies as proposed by Rosgen.  Procedures included the installation of a double wing deflector, removal of a mid-channel bar, installation of a cross vane and J-hook, and the construction of a bank full bench all as described in the Project Design section above. Root wads were also placed in the right bank at the lower end of the reach to protect the stream bank.

 

Linear Feet of Stream Restoration

400 feet

 

Linear Feet of Riparian Buffer Restored and/or Protected

800 feet

 

Buffer Vegetation

Native trees and shrubs were used to restore a 50ft-wide riparian buffer on Mr. Wood’s side of the stream.  Bare root vegetation was planted along the streambank.  Potted shrubs and wetland species were planted along the streambank above bankfull elevation.  Live stakes were used on critical slopes.

 

Brasstown Project Summary

Top of the Page

  Additional

Pictures

Copyright © 2004-2007 HRWC